6.2.1 General Information

Project Name
Applicability All Projects
Definition Name used for the project, if one is applicable
Units Text
Input Restrictions Input is optional for the proposed design
Baseline Rules Not applicable
Project Address
Applicability All projects
Definition Street address, city, state, and zip code
Units Text
Input Restrictions Input is mandatory for the proposed design
Baseline Rules Not applicable
Project Owner
Applicability All projects
Definition Owner(s) of the project or individual or organization for whom the building permit is sought. Information should include name, title, organization, email, and phone number
Units Data structure: Contact
Input Restrictions Input is optional for the proposed design
Baseline Rules Not applicable
Architect
Applicability All projects
Definition Architect responsible for the building design. Information should include name, title, organization, email, and phone number
Units Data structure: Contact
Input Restrictions Input is mandatory for the proposed design
Baseline Rules Not applicable
HVAC Engeneer
Applicability All projects
Definition HVAC Engineer responsible for the building design. Information should include name, title, organization, email, and phone number
Units Data structure: Contact
Input Restrictions Input is mandatory for the proposed design. Information should include name, title, organization, email, and phone number
Baseline Rules Not applicable
Lighting Engineer/Designer
Applicability All projects
Definition Lighting Engineer/Designer responsible for the building design. Information should include name, title, organization, email, and phone number
Units Data structure: Contact
Input Restrictions Input is mandatory for the proposed design
Baseline Rules Not applicable
Energy Modeler
Applicability All projects
Definition Individual responsible for performing the rating analysis. Information should include name, title, organization, email, and phone number
Units Data structure: Contact
Input Restrictions Input is mandatory for the proposed design
Baseline Rules Not applicable
Date
Applicability All projects
Definition Date of completion of the rating analysis or the date of its most-recent revision
Units Date format
Input Restrictions Input is mandatory for the proposed design